House Owner Pays Price for Contract Failure

Failure to make contractual terms clear is a surewere the contractual terms?
recipe for trouble and in construction contracts,3. If there was a binding contract or contracts, was
where the sums of money involved can beeither party to the dispute in breach of the
substantial, getting the contract terms agreed upcontract(s)? and
front is always sensible.4. If there was a breach of contract, what damages
In a recent case, a woman arranged with a propertyresulted?
developer that the developer should carry outThe court concluded that the woman had entered
refurbishment work on her property. Theinto two separate contracts with the developer. The
development of the property was to proceed infirst was with regard to the first phase of the works.
three stages and it was agreed that the developerShe had repudiated this contract when she regarded
would start the first phase as soon as the necessarythe developer’s breach of the contract as a
planning permission and building control permissionrepudiation of it. Her response had not been the
were obtained.correct one. She had herself created a repudiatory
The woman made up-front payments to coverbreach of contract by failing to pay the second
professional fees and to fund the commencement ofinstalments due under the contracts. The developer
the works. Unsatisfied with the subsequent progress,was therefore entitled to damages for the profits he
she demanded an account of how the money hadwould have made had the contracts been completed
been spent and decided that now was the time toand paid for as agreed.
have a formal contract. She refused to make furtherThis case shows how what may seem to be a
payments until a schedule of payments based onreasonable reaction – in this case declining to
progress achieved was agreed. The developermake payments when a development falls behind
refused to continue without further progressschedule – can lead to difficulties. In this case, the
payments. He sent a solicitor’s letter to theproblem was compounded by the woman’s
woman demanding payment of the sums due.response to the solicitor’s letter sent on behalf
Each side accused the other of repudiating the originalof the developer. Had the original contract contained
contract and eventually the dispute ended up in court.a clause which linked payments to the meeting of
The court had to decide the following issues:specific targets, then each side would have known
1. Was there a binding contract or contracts?where it stood and the dispute could probably have
2. If there was a binding contract or contracts, whatbeen avoided.